8
O&M Manual
Rev-H (8/11)
Part 2 – Mechanical Installation
The main installation requirements for ATI’s Turbidity Monitor are mechanical installation, and
connection of power to the monitor. Figure 1 on page 5 shows a schematic of a typical installation of a
complete system. The monitor should be located near the sensor in order to use the standard 30 foot
sensor cable supplied with the system. Longer cable runs can be accommodated using a junction box
and additional 7-conductor cable.
Figure 2 provides details on the mechanical installation of the standard panel mount electronic
assembly. The panel cutout must be made accurately as the cutout tolerance is small. Panel mounting
brackets are included with the monitor and are attached as shown below.
MOUNTING BRACKETS
(TYPICAL 2 PLACES)
MOUNTING BRACKET INSTALLATIONPANEL CUTOUT
3.60"
91.4mm
3.60"
91.4mm
Figure 2 - Panel Mount Monitor Dimensions & Installation